Electrical Panel Upgrade Cost in Long Beach, CA — 100A to 200A (2026)

Quick answer - Typical range (100A → 200A upgrade, installed, California): $2,200–$4,500+ - Most homeowners pay: $1,500–$4,000 nationally for a panel upgrade — Long Beach sits in the premium pricing tier (California is grouped with the highest-cost states), so plan on the upper half - Straightforward panel swap (same amperage, same location): $850–$2,200 depending on amperage and state tier - Complex jobs (new meter base, mast, relocation, or trenching): $3,500–$6,500+

The most common misunderstanding in panel pricing: the panel itself is cheap ($150–$250 for a 200A panel, per Angi's parts data). You are paying for labor, the service work around the panel, the permit, and utility coordination. That is also where quotes diverge — so compare scope, not just totals.

Cost breakdown by job type

Job Typical installed cost (2026)
100A panel replacement (same amperage) $850–$1,500 nationally; $1,500–$2,200 in premium-tier states incl. CA
100A → 200A upgrade (most common) $1,300–$3,000 nationally; $2,200–$4,500+ in CA-tier pricing
200A panel replacement (same amperage) $1,800–$3,500
200A → 400A upgrade $4,000–$6,500 nationally; higher in CA
Panel relocation (added to any job) Moves the job toward the top of its range — new wiring runs, patching, re-inspection

Sources: AllBetter 2026 panel guide; DIYProjects 2026 tier guide (California in Tier 4 "Premium"); Angi panel data — see Sources.

Common add-ons, priced separately

Add-on Typical cost
Whole-home surge protector $300–$600
Generator interlock kit $400–$800
Level 2 EV charger circuit (240V) $600–$1,500
Smart energy monitor $400–$700
New meter base / service entrance work The main driver that pushes a $3,000 job toward $5,000

Factors that move the price in Long Beach

Permits in Long Beach

A panel upgrade requires an electrical permit and inspection in Long Beach — no exceptions for "just swapping the box." Your electrician pulls it; unpermitted panel work reliably surfaces at home sale and can complicate insurance claims.

From the City of Long Beach's own published Electrical Permit & Plan Check Fee schedule (longbeach.gov): electrical permit minimum fee $100; service 600V or less, up to and including 200 amps, $23 per service; panels $17 per panel; each additional meter $7. Plan-check minimums also apply on some scopes (the schedule lists plan-check minimums starting at $216 for applicable work). (Fee schedules are revised periodically — the city's schedule is the authority, and your electrician's quoted permit total is confirmed at issuance. The city fees themselves are a small part of this project's cost; if a quote shows a very large "permit" line, ask for the breakdown.)

The sequence on a real job: permit → SCE disconnect scheduled → install (same day) → city inspection → SCE reconnect/final. Power is typically off 4–8 hours on install day.

5 ways not to overpay

  1. Demand the load calculation. If 200A isn't justified by your actual loads and planned additions, a like-for-like panel replacement at your current amperage can cost half as much.
  2. Compare scope, not totals. One bid includes meter base, mast, grounding, and patching; another quietly excludes all four. Put both bids in the same columns before comparing.
  3. Bundle the add-ons now, not later. An EV circuit or surge protector added during the upgrade is priced as an add-on. The same work as a separate visit later is priced as a new job.
  4. Don't pay for AFCI-everything upsells without a code citation. Requirements for existing circuits during a panel change vary by jurisdiction and code cycle. If a quote lists expensive "code-required" extras, ask which code section requires them.
  5. Verify the C-10 license and who pulls the permit. Electrical work in California requires a C-10 electrical contractor license. The permit should be in the contractor's name, and you should get the permit number before work starts.

FAQ

How long does a 100A to 200A upgrade take from start to finish? The physical install is usually one day, with power off roughly 4–8 hours. The full process — permit, SCE scheduling, install, inspection, reconnect — commonly runs several weeks end to end, and most of that is scheduling neither you nor your electrician controls.

Do I really need 200 amps? If you're adding an EV charger, heat pump, electric range, ADU, or solar, very likely yes — 100A service runs out of headroom fast with two or more of those. If none of those are planned and your breakers aren't tripping, a same-amperage panel replacement may be all you need. The load calculation is the honest way to decide.

Will a panel upgrade raise my home's value? It removes an objection more than it adds a premium: obsolete panels (especially FPE/Zinsco) get flagged by inspectors and can stall escrow or insurance placement. A permitted 200A service makes the home easier to sell and insure, and enables the electrification upgrades buyers increasingly ask about.

Can I stay in the house during the work? Yes — but plan for a workday without power: no AC, no Wi-Fi, refrigerator doors closed. Most homeowners run errands or work elsewhere for the 4–8 hour window.

What if SCE says my service needs more than a panel? Sometimes the utility-side equipment (service drop, transformer capacity, underground lateral) becomes the constraint, and that work follows SCE's process and timeline, not your electrician's. Your electrician should tell you early — after the meter spot/load review — if your address has that complication, because it changes both schedule and who pays for what.

Get quotes

Contractor in Long Beach? This guide is part of a new verified-pros directory for Long Beach. Listings are free and limited to CSLB-verified licenses. Claim yours: email xavier@altapointdevelopment.com with subject "Directory listing claim".


Sources

Prices are 2026 planning ranges from the sources above, not quotes. Scope — especially meter, mast, and service-entrance work — is what separates a $2,500 job from a $5,000 one.

Run the numbers: Field Calculators — free calculators for the rest of the project list.